On 11 October 2023, we entered into a contract with Synthesia, a.s., as a general contractor. Following a public tender, we were awarded a „turnkey“ contract. The main subject of the contract is the delivery of a new steam condensing turbine with generator with an output of 25 MWe with two regulated extraction in connection with the existing heating plant technology and steam system.
The contract includes the complete dismantling and replacement of the existing TG14 turbogenerator technology including its heaters, piping, accessories and electrical substations for TG14.
EKOL, spol. s r.o. is a respected European manufacturer and supplier of heat and power generating plants...
30 years of ShaanGu EKOL company
Video links in
CZE,
PL,
ARAB
Bioelectric plant in Sviadnov
Video links in
CZE,
GER
On 27 April 2024, we are the supplier of the sugar mill's Energo Centre...