Company | Reference | Project / Site | Pc | Year of Realization |
---|---|---|---|---|
Yingyuan Group / ShaanGu |
"Planning, design, manufacture, supervision of erection and commissioning of a 35,6 MW condensing steam turbine with controlled extraction for compressor drive, type specification EST 50 CE" |
Jingyuan / Cina | 1 | 2022 |
Astaldi S.p.A. and TME.E. S.p.A. |
Design, construction, production, delivery, assembly and commissioning of a steam condensing turbine with regulated consumption to drive a generator in a municipal waste incinerator 18 MW, type P18-4.0 / 0.1E / EST 30CE / |
Gdańsk / Poland | 1 | 2022 |
Megatem / Energoservis Lublin |
Planning, design, manufacture, supervision of erection and commissioning of 12 MW backpressure steam turbine for generator drive, type specification EST 30B |
Lublin / Poland | 1 | 2021 |
Energika |
Design, construction, production, assembly and commissioning of a 3.3 MW condensing steam turbine for generator drive. |
Lomza / Poland | 1 | 2021 |
Shandong Jinmei Mingshui Chemical 30000 Nm3/h / ShaanGu |
Design, construction, production, supply and commissioning of a 27.8 MWe steam condensing turbine, type EST40C / K27.8-8.9 E |
Mingshui / China | 1 | 2021 |
Yingde Gases Group |
Design, construction, production, supply and commissioning of a steam condensing turbine to drive a 42.5 MW compressor, type K42.5-8.9E |
Yinan / China | 1 | 2021 |
Jingyuan Coal Industry Group Liuhua Chemical Co. / ShaanGu |
Planning, design, manufacture, supervision of erection and commissioning of a 35,6 MW condensing steam turbine with controlled extraction for compressor drive, type specification EST 50 CE |
Jingyuan / China | 1 | 2022 |
Grupa AWW |
Planning, design, manufacture, supervision of erection and commissioning of a 9,8 MWe backpresssure steam turbine for generator drive, type specification EST 30 B |
Zbiersk / Poland | 1 | 2021 |
Wanhua Chemical Group Co. - MALEIC / ShaanGu |
Planning, design, manufacture, supervision of erection and commissioning of a 20,6 MW backpressure steam turbine with controlled extraction, type specification EST 50 BE |
Maleic / China | 1 | 2021 |
PROKON / Erdemir |
Planning, design, manufacture, supervision of erection and commissioning of a 18.7 MW condensing steam turbine for compressor drive, type specification EST 40C |
Erdemir / Turkey | 1 | 2021 |
Chongqing Huafeng Chemical Co., ltd |
Planning, design, manufacture, supervision of erection and commissioning of a 10,7 MW condensing steam turbine for compressor drive, type specification EST 30C |
Chongqing / China | 1 | 2021 |
Energika |
Planning, design, manufacture, supervision of erection and commissioning of 6,9 MW condensing steam turbine for generator drive, type specification EST 30CE |
Eco Raven / Poland | 1 | 2021 |
Yingde Gases Group |
Planning, design, manufacture, supervision of erection and commissioning of a 28 MW condensing steam turbine for compressor drive, type specification EST 40C |
Mingshui 2 / China | 1 | 2022 |
Synthos Dwory 7 Sp. z o.o., Sp. j. |
Planning, design, manufacture, supervision of erection and commissioning of 31,7 MW backpressure steam turbine for generator drive, type specification EST 50BE |
Synthos Dwory / Poland | 1 | 2021 |
Wanhua Chemical Group |
Planning, design, manufacture, supervision of erection and commissioning of 8 MW backpressure steam turbine for generator drive, type specification EST 30B |
Fujian Wanhua / China | 1 | 2021 |
Yingde Gases Group |
Planning, design, manufacture, supervision of erection and commissioning of 42 MW condensing steam turbine for compressor drive, type specification EST 50C |
Jinan / China | 1 | 2021 |
Astaldi S.p.A. and TME.E. S.p.A. |
Planning, design, manufacture, supervision of erection and commissioning of 18 MW condensing steam turbine for generator drive, type specification EST 40CE |
Gdaňsk / Poland | 1 | 2021 |
Energoservis Lublin |
Planning, design, manufacture, supervision of erection and commissioning of 12 MW backpressure steam turbine for generator drive, type specification EST 30B |
Megatem Lublin / Poland | 1 | 2021 |
Yantai Wanhua Chemical Co., ltd |
Návrh, konstrukce, výroba, dodávka a uvedení do provozu parní kondenzační turbíny k pohonu kompresoru 8,9 MW, typ K8,9-4,0E |
Yantai II / Čína | 1 | 2021 |
Yantai Wanhua Chemical Co., ltd |
Planning, design, manufacture, supervision of erection and commissioning of 8,9 MW condensing steam turbine for compressor drive, type specification K8,9-4,0E |
Yantai II / China | 1 | 2020 |
Shanxi Gaoyi Steel Co., ltd |
Planning, design, manufacture, supervision of erection and commissioning of 30 MW condensing steam turbine for compressor drive, type specification K30.1-8,8E |
Yuncheng / China | 1 | 2020 |
Chongqing Huafeng Chemical Co., ltd | Planning, design, manufacture, supervision of erection and commissioning of 10 MW condensing steam turbine for compressor drive, type specification K10.1-4.0E |
Chongqing / China | 1 | 2019 |
HSFC Samut | Planning, design, manufacture, erection and commissioning of 25 MW backpressure steam turbines for generator drive, type specification EST 40 B |
Bangkok / Thailand | 1 | 2019 |
HSFC Samut | Planning, design, manufacture, erection and commissioning of 6,5 MW condensing steam turbines for generator drive, type specification EST 30 CE |
Bangkok / Thajsko | 1 | 2019 |
KERNEL Group | Planning, design, manufacture, erection and commissioning of 13,6 MW condensing steam turbines for generator drive, type specification EST 30 CE |
Bandurka / Ukraine | 1 | 2019 |
KERNEL Group | Planning, design, manufacture, erection and commissioning of 12,1 MW condensing steam turbines for generator drive, type specification EST 30 CE |
Volchansk / Ukraine | 1 | 2019 |
KERNEL Group | Planning, design, manufacture, erection and commissioning of 23,75 MW condensing steam turbines for generator drive, type specification EST 30 CE |
Pridneprovskiy / Ukraine | 1 | 2019 |
Etihad Food Industries, Co. |
Planning, design, manufacture, erection and commissioning of 20 MW condensing steam turbines for generator drive, type specification EST 30 CE, part of EPC project |
Babylon / Iraq | 2 | 2018 |
E.S.I.I.C Egypt |
Planning, design, manufacture, erection and commissioning of 6 MW backpressure steam turbines for generator drive, type specification EST 30 B |
Kom-Ombo / Egypt | 1 | 2018 |
Barlinek Inwestycje Sp. z o.o. |
Planning, design, manufacture, erection and commissioning of 5,8 MW backpressure steam turbines for generator drive, part of EPC Project | Barlinek / Poland | 1 | 2017/2018 |
BIOMASS TO ENERGY BENKOVAC d.o.o. | Planning, design, manufacture, erection and commissioning of 5,6 MW condensing steam turbine for generator drive, part of EPC Project | Benkovac / Croatia | 1 | 2016/2017 |
JAZAN SUGAR Refinery | Planning, design, manufacture, erection and commissioning of 7 MW backpressure steam turbines for generator drive, type specification typ EST 30 B |
Jazan / Saudi Arabia | 2 | 2016/2017 |
WANHUA Chemical Yantai | Planning, design, manufacture, erection and commissioning of 8,9 MW condensing steam turbine for generator drive, type specification EST 30 C | Yantai / China | 1 | 2016 |
SHCHEKINO AZOT | Planning, design, manufacture, erection and commissioning of 2,4 MW condensing steam turbine for pump drive power, type specification EST 20 C | Shchekino / Russia | 1 | 2016 |
SHAANXI Qin-feng Gas | Planning, design, manufacture, erection and commissioning of 25 MW condensing steam turbine for compressor drive, type specification EST 40 C |
Mingshui / China | 2 | 2015 |
Soda Polska Ciech Inowroclav | Planning, design, manufacture, erection and commissioning of 10,5 MW backpressure steam turbine for generator drive, type specification EST 40 BE |
Soda Inowrolav / Poland | 1 | 2015 |
Mostostal Varšava | Planning, design, manufacture, erection and commissioning of 15 MW condensing steam turbine for generator drive, type specification EST 40 CE |
Szczecin / Poland | 1 | 2014 |
KPS Ria Brno | Planning, design, manufacture, erection and commissioning of 25 MW condensing steam turbine for generator drive, type specification PT25,2-9,7/1,1/0,4 | Lovochemie / Czech Republic | 1 | 2014 |
E.S.I.I.C. Cairo | Planning, design, manufacture, erection and commissioning of 3,8 MW backpressure steam turbine for generator drive, type specification R3,8/3,85-(2,36-2,55)/0,28 | Quous 2 / Egypt | 1 | 2014 |
BUDIMEX | Planning, design, manufacture, erection and commissioning of 9 MW condensing steam turbine for generator drive, type specification T9-4,0/017 | ZUOK Bialystok / Poland | 1 | 2014 |
ETIHAD Food Industries | Planning, design, manufacture, erection and commissioning of 10 MW backpressure steam turbine for generator drive, type specification R10-4,5/0,25 | ETIHAD Sugar Refinery / Iraq | 2 | 2014 |
Heat Plant Loučovice |
Planning, design, manufacture, erection and commissioning of 7,5 MW condensing steam turbine for generator drive, type specification K7,5-6,5/1,0 | Loučovice / Czech Republic | 1 | 2014 |
SCS Proyectos | Planning, design, manufacture, erection and commissioning of 4 MW backpressure steam turbine for generator drive, type specification PR4-10,6/3,32/0,686 | Cosoleasaque Veracruz / Mexico | 1 | 2013 |
ČKD Kompresory | Planning, design, manufacture, erection and commissioning of 14 MW condensing steam turbine for compressor drive, type specification P14-4,05/2,35 | ČKD Kompresory / Czech Republic | 1 | 2013 |
SEA Kolín | Planning, design, manufacture, erection and commissioning of 6,5 MW condensing steam turbine for generator drive, type specification K6,5-4,5 | IZOL Kolín / Czech Republic | 1 | 2013 |
ELSACO Botosani | Planning, design, manufacture, erection and commissioning of 3,5 MW steam turbine for generator drive, type specification K3,5—5/0,06-0,24 | CET Bacau / Romania | 1 | 2013 |
KAZANCOMPRESSORMASH | Planning, design, manufacture, erection and commissioning of 3,5 MW condensing steam turbine for compressor drive, type specification K3,5-3,14 | Kazaň 2 / Russia | 1 | 2013 |
Energo Future | Planning, design, manufacture, erection and commissioning of Biomassa Power Plant inclusive 5,8 MW backpressure steam turbine with generator, type specification R5,8 – 6,2/0,04-0,12 | Sviadnov / Czech Republic | 1 | 2012 |
A6 Impex | Planning, design, manufacture, erection and commissioning of 9,7 MW condensing steam turbine with generator, type specification P9,7 – 4,1/0,2 | DEJ Rumunsko / Romania | 1 | 2012 |
Mostostal | Planning, design, manufacture, and commissioning of 25 MW condensing steam turbine with two controlled extractions, type specification T 25 – 9,0/0,1 | Elblag / Poland | 1 | 2012 |
EnergoPromCity | Planning, design, manufacture, and commissioning of 14 MW condensing steam turbine for compressor drive, type specification K14 – 1,0 | Ekibastuz / Kazachstan | 1 | 2012 |
Energetika Dwory | Planning, design, manufacture, erection and commissioning of 27,5 MW backpressure steam turbine with generator, type specification PR 27,5-7,8/1,4/0,4 | Dwory / Poland | 2 | 2012 |
Fabian-Vanko | Planning, design, manufacture, erection and commissioning of 7 MW condensing steam turbine with generator, type specification P7,0 – 3,7/0,2 | Badín / Slovakia | 1 | 2011 |
TENZA, a.s. | Planning, design, manufacture, erection and commissioning of 2,9 MW condensing steam turbine with generator, type specification T2,9-3,15/0,12 | Mydlovary / Czech Republic | 1 | 2011 |
Bučina Zvolen | Planning, design, manufacture, erection and commissioning of 5,4 MW condensing steam turbine with generator, type specification P5,4-2,9/1,0 | Bučina Zvolen / Slovakia | 1 | 2012 |
KAZANCOMPRESSORMASH | Planning, design, manufacture, erection and commissioning of 4,5 MW condensing steam turbine for compressor drive, type specification K4,5 – 2,65 | Kazaň 1 / Russia | 1 | 2011 |
Energy Edge ZC,spol.s.r.o | Planning, design, manufacture and commissioning of 11 MW condensing steam turbine with generator, heat exchanger and other accesories,type specification K 11,1 - 6,8 | Žarnovica / Slovakia | 1 | 2012 |
Teplárna České Budějovice | Planning, design, manufacture and commissioning of 12 MW condensing steam turbine with generator, heat exchanger and other accesories, type specification K12 - 0,78 | České Budějovice / Czech Republic | 1 | 2011 |
Carthamus, a.s. | Planning, design, manufacture and commissioning of 8,45 MW condensing steam turbine with generator, heat exchanger and other accesories, type specification T 8,45 - 6,5/0,6 | Domoradice / Czech Republic | 2 | 2012 |
E.S.I.I.C cukrovar | Planning, design, manufacture erection and commissioning of 6 MW backpressure steam turbine with generátor, type specification R6 – 2,3/0,3. | Qous / Egypt | 1 | 2010 |
E.S.I.I.C. cukrovar | Planning, design, manufacture erection and commissioning of 6 MW backpressure steam turbine with generátor, type specification R6 – 2,3/0,3. | EDFU / Egypt | 1 | 2010 |
Teplárna Dalkia Kolín, a.s. | Planning, design, manufacture, erection and commissioning of rotating reduction for boiler 0,7 MW | Kolín / Czech Republic | 1 | 2009 |
ACTHERM, s.r.o. | Planning, design, manufacture and commissioning of 20 MW condensing steam turbine with two controlled extractions, type specification PT 20 - 3,7/0,6/0,15. | Chomutov / Czech Republic | 1 | 2009 |
Nile Sugar Copany Cairo | Supply of two 8 MW backpressure steam turbines, type specification R8-4,5/0,3 | Alexandria / Egypt | 2 | 2009 |
EC Kielce | Planning, design, manufacture and commissioning of 10 MW condensing steam turbine with generátor, heat exchanger and other accesories, type specification R 10,8 - 5,3/0,04-0,12. | Kielce / Poland | 1 | 2008 |
PEC | Planning, design, manufacture and commissioning of 7,35 MW backpressure steam turbine with heat exchanger type specification R7,35 - 4,0/0,0439. | Suwalki / Poland | 1 | 2008 |
Dalkia | Modification of 12 MW condensing steam turbine generátor aimed at power increase by 1 MW, type specification P 12-4,1/1,1 | Elektrárna Kolín / Czech Republic | 1 | 2007 |
Anwil | Planning, design, manufacture and commissioning of 1,6 MW backpressure steam turbine, type specification R 1,6 - 3,0/0,8. | Wloclawek / Poland | 1 | 2007 |
Thajsko II | Retrofit of backpressure steam turbine with one controlled extraction, type specification R 36 - 11,5/0,6-E. | Bangkok / Thailand | 1 | 2007 |
Jitka Otín | Planning, design, manufacture and commissioning of 5,6 MW condensing steam turbine with one controlled extraction, type specification T 5,6 - 3,8/0,3. | Jindřichův Hradec / Czech Republic | 1 | 2007 |
Tp Tábor | Planning, design, manufacture and commissioning of 10 MW condensing steam turbine, type specification T 10,5 - 1,0/0,25. | Tábor / Czech Republic | 1 | 2006-2007 |
Nobaria Sugar and Rafining company | Planning, design, manufacture and commissioning of 8 MW backpressure steam turbine, type specification R 8 - 4,5/0,3E. | Nobaria / Egypt | 2 | 2006-2007 |
Borken | Planning, design, manufacture and commissioning of 6,5 MW condensing steam turbine, type specification K 6,5 - 5,2. | Borken / Germany | 1 | 2006 |
HSFC Co. Ltd. Bangkok | Delivery of 20,4 MW backpressure steam turbine including generátor, type specification R 20,4 - 9,0/0,6-E | Bangkok / Thailand | 1 | 2006 |
ADATO | Planning, design, manufacture and commissioning of 5,4 MW condensing steam turbine, type specification K 5,4 - 2,1. | Banská Bystrica / Slovakia | 1 | 2006 |
ADATO | Planning, design, manufacture and commissioning of 1,64 MW backpressure steam turbine, type specification R1,54-6,3/2,3. | Banská Bystrica / Slovakia | 1 | 2006 |
Sokolovská uhelná, a. s. | Revision and repair of 60 MW condensing steam turbine, type specification PP 57 - 6,6/3,5/0,55. | Vřesová / Czech Republic | 1 | 2006 |
Sokolovská uhelná, a.s. | Moderniztion of turbine, replacement of inlet extensions, reblading of some rows of 55 MW condensing steam turbine, type specification PP 55 - 13,0/3,5/0,5 T17/17- 1,8/0,12. | Vřesová / Czech Republic | 1 | 2006 |
Energetika Třinec | Overhaul und reblading of 17 MW steam turbine type specification | Třinec / Czech Republic | 1 | 2006 |
SI.I.C Cairo | Planning, design, manufacture and commissioning of 1 MW backpressure steam turbine with gearbox for sugar mill, type specification TR 700 hsf. | Abou-Kourkas / Egypt | 1 | 2005 |
S.I.I.C.Cairo | Planning, design, manufacture and commissioning of backpressure steam turbine type specification R 6 - 2,3/0,3. | Armant / Egypt | 1 | 2005 |
COLTERM Dinuinstal | Planning, design, manufacture and commissioning of backpressure steam turbine, type specification ER 19,7 - 1,4/0,3 for generátor drive. | Timisoara / Romania | 1 | 2005 |
Škoda Power, s.r.o. | Supply of spare parts, modification, erection and commissioning of 33 MW steam turbine type specification PT 33 - 9,0/1,2/0,5. | Dalkia Ostrava / Czech Republic | 1 | 2005 |
ČKD Nové Energo, a.s. | Modernization, modification, and repair of 11 MW condensing steam turbine, type specification T 11/9,5 - 15,0/2,0 for blastfurnace compressor drive. | Energetika Třinec / Czech Republic | 1 | 2005 |
Sokolovská uhelná, a. s. | Overhaul and repair of 55 MW backpressure steam turbine, type specification PR 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2005 |
Sokolovská uhelná, a. s. | Overhaul and repair of 55 MW condensing steam turbine, type specification PP 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2005 |
ACETOIndustries | Update of hydraulic governing system in ŠKODA 110 MW steam turbine. | KAFR EL DAWAR / Egypt | 1 | 2004 |
DALKIA ČR, a. s. | Complete overhaul of 13 MW turbine. | Ostrava / Czech Republic | 1 | 2004 |
Teplárna České Budějovice | Complete overhaul of R 25 - 9,0/1,0 steam turbine including new blading. | České Budějovice / Czech Republic | 1 | 2004 |
Ško-Energo, a. s. | Repair of 44 MW condensing steam turbine. | Mladá Boleslav / Czech Republic | 1 | 2004 |
Sokolovská uhelná, a. s. | Overhaul and repair of 55 MW condensing steam turbine, type specification PP 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2004 |
ZRE KatoviceS.A. | Inspection of 5 MW condensing steam turbine. | Katovice / Poland | 1 | 2003 |
Vihorlat s.r.o. | Inspection and repair of 6 MW condensing steam turbine, type specification P 6 - 4,0. | Snina / Slovakia | 1 | 2003 |
Martinská teplárenská, a.s. | Overhaul of 12 MW steam turbine, type specification PR 12/7 - 5,4/0,8/0,12. | Martin / Slovakia | 1 | 2003 |
SES, a. s.Tlmače | Planning, design, manufacture and commissioning of backpressure steam turbine, type specification ER 5,5 - 13/1,4 for turbo-feed pump drive, 200 MW unit powerplant Starobeshevo. | Powerplant Starobreshevo / Ukraine | 1 | 2003-2004 |
Ško-Energo, a. s. | Repair of 44 MW condensing steam turbine. | Mladá Boleslav / Czech Republic | 1 | 2003 |
ACTHERM Chomutov s.r.o. | Overhaul of 6 MW backpressure steam turbine, type specification R6 - 3,5. | Chomutov / Czech Republic | 1 | 2003 |
Chemopetrol Litvínov, a.s. | Overhaul of 16 MW condensing steam turbine, type specification K 16,5 - 4,5. | Litvínov / Czech Republic | 1 | 2003 |
Sokolovská uhelná, a.s. | Overhaul of 55 MW backpressure steam turbine, type specification PR 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2003 |
Schering AG | Planning, design, manufacture, supply, commissioning of backpressure steam turbine with starting condenser, with controlled extraction, type specification PR 10,3 - 7,3/0,5-0,23E | Berlin / Germany | 1 | 2003 |
Cinergetika Ú/L | Revision and repair of 6 MW backpressure steam turbine, type specification PR 8,6 - 6,00/1,5/0,7. | Ústí n/L / Czech Republic | 1 | 2002 |
Sokolovská uhelná, a.s. | Revision and repair of 60 MW condensing steam turbine, type specification PP 57 - 6,6/3,5/0,55. | Vřesová / Czech Republic | 1 | 2002 |
Sokolovská uhelná, a.s. | Revision and repair of 55 MW condensing steam turbine, type specification PP 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2002 |
BKH | Planning, design, manufacture, delivery, comissioning of condensing steam turbine, type specification K 5 - 4. 9000min-1. | Grossaitingen / Germany | 1 | 2002 |
Kronospan | Planning, design, manufacture, delivery, comissioning of condensing steam turbine, type specification K 5,5 - 3,1. 9000min-1 | Lampertswalde / Germany | 1 | 2002 |
Actherm Chomutov a.s. | Overhaul of 12 MW condensing steam turbine with automatic double extraction, type specification PT 12 - 3,5/1,3/0,12. | Chomutov / Czech Republic | 1 | 2002 |
MEGATEM EC. Lublin | Overhaul of 15 MW steam turbine. | Lublin / Poland | 1 | 2002 |
Slovenské cukrovary, a. s. | Revision and repair of 10 MW backpressure steam turbine, type specification R 10 - 5,9/0,7. | Sereď / Slovakia | 1 | 2001 |
Lovochemie, a.s. | Revision and repair of 9 MW condensing steam turbine, type specification PP 9 - 3,7/1,1/0,4. | Lovosice / Czech Republic | 1 | 2001 |
Žilinská teplárenská, a. s. | Revision and repair of 12 MW backpressure steam turbine, type specification R 12 - 9,0/1,3. | Žilina / Slovakia | 1 | 2001 |
Zvolenská teplárenská, a. s. | Revision and repair of 25 MW backpressure steam turbine, type specification R 25 - 13,0/1,3. | Zvolen / Slovakia | 1 | 2001 |
Žďas, a.s. | Revision and repair of 6 MW condensing steam turbine ŠKODA, type specification P 6 - 3,5/0,4. | Žďár n/Sázavou / Czech Republic | 1 | 2001 |
Energetika Třinec, a.s. | Rekonstruction and reblading of 10 MW condensing steam turbine, type specification T 9,8 -1,8/0,12. | Třinec / Czech Republic | 1 | 2001 |
MVA | Project, design, manufacture, delivery, putting into operation of 5,6 MW, backpressure steam turbine, type specification R 5,6 - 3,8/0,32 | Bielefeld / Germany | 1 | 2001 |
Elektrárna Kolín, a.s. | Project, design, manufacture, delivery, putting into operation of 560 kW, backpressure steam turbine, type specification R 0,56 - 1,1/0,2. | Kolín / Czech Republic | 1 | 2001 |
Sokolovská uhelná, a.s. | Inspection and repair of 55 MW condensing steam turbine, type specification PP 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2001 |
Sokolovská uhelná, a.s. | Inspection and repair of 60 MW condensing steam turbine, type specification PP 57 - 6,6/3,5/0,55. | Vřesová / Czech Republic | 1 | 2001 |
S.I.I.C.Cairo | Planning, design and manufacture, delivery, commisioning of 4,5 MW backpressure steam turbine, type specification R 4,5 - 2,2/0,3. | Kous / Egypt | 1 | 2000 |
Cinergetika Ú/L | Turbine modification, modernization, power increase from 6 MW to 8,6 MW, turbine base plate modification, generátor replacement (biger output), type specification PR 8,6 - 6,0/1,5/0,7. | Ústí nad Labem / Czech Republic | 1 | 2000 |
Teplárna Otrokovice, a.s. | Overhaul and connection to the 25MW backpressure parent kontrol systém, type specification PR 25 - 9,0/1,5/0,7. | Otrokovice / Czech Republic | 1 | 2000 |
Sokolovská uhelná, a.s. | Turbine modernization, replacement of parts in turbine steam inlet section, reblading of some rows of 55MW turbine. Type specification PP 55 - 13,0/3,5/0,5. | Vřesová / Czech Republic | 1 | 2000 |
LOBBE, Switzerland | Planning, design and manufacture of condensing steam turbine with 14500/1500 gearbox, type specification K 1,6 - 2,0. | Dąbrowa Górnicza / Poland | 1 | 2000 |
Moravskoslezské teplárny, a.s. | 12 MW backpressure steam turbine modification and reblading, type specification R 12 - 3,6/0,25. | Karviná / Czech Republic | 1 | 2000 |
Kaučuk, a.s. | Planning, design, manufacture and delivery of 25 MW h.-p. stage for 30 MW condensing steam turbine, reblading of m.-p. and I.-p. stages. Power increase from 30 MW to 33 MW, type specification PT 33-9,0/1,0/0,12. | Kralupy n/Vltavou / Czech Republic | 1 | 2000 |
Vihorlat, a.s. | 6 MW condensing steam turbine inspection and repair, type specification P 6 - 3,5/0,6 (ŠKODA). | Snina / Slovakia | 1 | 2000 |
Cukrovar NOVA, a.s. | 10 MW backpressure steam turbine inspection and repair, type specification R 10 - 5,9/0,7. | Sereď / Slovakia | 1 | 2000 |
SSE š.p. Žilina, závod Tepláreň Martin | 32 MW backpressure steam turbine repair, turbine base plate modification. Type specification PR 32 - 9,0/0,8/0,17. | Martin / Slovakia | 1 | 2000 |
Slovenské elektrárne, a.s. | 32 MW condensing steam turbine overhaul, oil system and control system modification - type specification T 32 - 6,95/0,25. | Nováky / Slovakia | 1 | 2000 |
Povážské strojárne, a.s. - Energetika | Overhaul of 6 MW backpressure steam turbine, reblanding, type specificaton R 6 - 3,5/0,6. | Povážská Bystrica / Slovakia | 1 | 2000 |
Vihorlat, a.s. | Overhaul and repair of 6 MW back-pressure turbine, type specification R 6 - 3,5/0,5. | Snina / Slovakia | 1 | 1999 |
Tp Bratislava | PR 6,4 - 1,6/0,7 steam turbine repair. | Bratislava / Slovakia | 1 | 1999 |
LOVOCHEMIE,a .s. | General overhaul of PP 9 - 3,7/1,1/0,4 steam turbine. | Lovosice / Czech Republic | 1 | 1999 |
KUTNOHORSKÁ a.s. | Planning, design, manufacture, supply and comiisioning of P 12 - 4,1/1,1 condensing steam turbine with one controlled extraction, 12 MW output. . | Kolín / Czech Republic | 1 | 1998 |
ELEKTRÁRNA POČERADY | Modification of D 7,5 turbines for feed water pump driving. | Počerady / Czech Republic | 5 | 1998 |
VYTOPNA FRÝDEK-MÍSTEK | Modification and instrallation of Bergmann-Borsig turbine including piping, replacement of control system for WOODWARD systém. | Frýdek Místek / Czech Republic | 1 | 1997 |
VYTOPNA FRÝDEK-MÍSTEK | Conversion of heating plant into power and heating plant. Supply and installation of steam turbine, step-down station and heat exchangers. | Frýdek Místek / Czech Republic | 1 | 1997 |
TEPLÁRNA OTROKOVICE, a.s. | Modification of PR 25 steam turbine - HP part reblanding, replacement of control systém for WOODWARD systém, replacement of monitoring system for BENTLY NEVADA system. | Otrokovice / Czech Republic | 1 | 1997 |
KARLOVARSKÁ TEPLÁRENSKÁ, a.s. | General overhaul of MV 550 steam turbine. | Karlovy Vary / Czech Republic | 1 | 1996 |
OSTROVSKÁ TEPLÁRENSKÁ, a.s. | Modification of ER/6 - 3,5/0,68 back-pressure steam turbine | Ostrov / Czech Republic | 1 | 1996 |
SELIKO, a.s. | General overhaul R1,5 - 3,5/0,35 steam turbine. | Kojetín / Czech Republic | 1 | 1995 |
OLŠANSKÉ PAPÍRNY, a.s. | General overhaul R1,5 -3,7/0,6 steam turbine. | Olšany / Czech Republic | 1 | 1995 |
LOVOCHEMIE a.s. | EPR 4/4-3,9/1,1/0,4 steam turbine supply | Lovosice / Czech Republic | 1 | 1996 |
HARMANECKÉ PAPIERNE, a.s. | EPR 2/2 - 3,6/1,1/0,4 steam turbine overhaul | Harmanec / Slovakia | 1 | 1996 |
JITKA a.s. | PR 2,8/2,8 - 3,5/0,6/0,18 steam turbine overhaul. | Jindřichův Hradec / Czech Republic | 1 | 1995 |
TEPLÁRNA TRMICE a.,s. | Adjustment of 12,75/1,67 steam turbine control system. | Ústí n/L / Czech Republic | 1 | 1995 |
SANBORN a.s. | Overhaul of nozzle segments and trial run of R16 - 12,75/1,67 steam turbine. | Velké Meziříčí / Czech Republic | 1 | 1995 |
ČEZ,a.s. Elektrárny Poříčí | General overhaul of K5 - 0,5 turbine. | Teplárna Náchod / Czech Republic | 1 | 1995 |
OLŠANSKÉ PAPÍRNY a.s. | Technical assistance during R1,5/3,7/0,6 steam turbine overhaul. | Olšany / Czech Republic | 1 | 1995 |
TONUS a.s. | Adjustment of R1,5 - 3,5/0,45 steam turbine control system. | Jaroměř / Czech Republic | 1 | 1994 |
Tlaková plynárna Ústí n/L | R12 - 3,2/0,4 steam turbine repair. | Ústí n/L / Czech Republic | 1 | 1994 |
Seliko Kojetín | Repair of R1,5 - 3,5/0,35 steam turbine control system | Kojetín / Czech Republic | 1 | 1994 |